Verizon Wireless Florence, SC

Renovation

Status

Accepting Bids

Bid Date 4/16/25 5:00pm

Company

...

Location

24111 David H. Mcleod Blvd Florence, SC 29501

*** THIS PROJECT REQUIRES NIGHTS AND WEEKEND WORK ***

FACILITY TO REMAIN OPERATIONAL DURING ALL CONSTRUCTION ACTIVITIES

This project will be in TWO PHASES, with all loud/obtrusive work to be completed after hours. We are not

required to build a wall separating the phases however, we would like a clean white heavy plastic barrier

that is firmly attached at both the top and the bottom. The project is anticipated to last 8 weeks depending

on progress and inspections. We anticipate each phase taking approximately (4) weeks including fixture

installation to complete.