Verizon Wireless Florence, SC
Renovation
Status
Accepting Bids
Bid Date | 4/16/25 5:00pm |
Company
...
Location
24111 David H. Mcleod Blvd Florence, SC 29501
*** THIS PROJECT REQUIRES NIGHTS AND WEEKEND WORK ***
FACILITY TO REMAIN OPERATIONAL DURING ALL CONSTRUCTION ACTIVITIES
This project will be in TWO PHASES, with all loud/obtrusive work to be completed after hours. We are not
required to build a wall separating the phases however, we would like a clean white heavy plastic barrier
that is firmly attached at both the top and the bottom. The project is anticipated to last 8 weeks depending
on progress and inspections. We anticipate each phase taking approximately (4) weeks including fixture
installation to complete.